On July 21, 2011 LPPX wrote:getting bunny suited for mylar main insulator assembly
Man, what have you done......
Since reading your post I have in front of me the picture of Eric Lerner dressed in a playboy bunny suit working on the FF1 switches.
I'll need professional help to get it removed from my brain....
AaronB wrote:First cleaning shot successful. Data acquisition done. Preparing for next shot. Nice to be operational again!
Indeed.
I'm not sure if they've fired all switches at 45 kV yet, though. If not, it should be soon. Then, hopefully, it won't be too long before they can move beyond deuterium.
Temperature, density, confinement time: pick any two.
Ivy Matt wrote:
I'm not sure if they've fired all switches at 45 kV yet, though. If not, it should be soon. Then, hopefully, it won't be too long before they can move beyond deuterium.
They're starting out at 35kv while they chase bugs and tweak the system but then they will up it to 45.
On August 5, 2011 LPPX wrote:Switch tuning progressing well
On August 7, 2011 LPPX wrote:12/12, all together now!
On August 8, 2011 LPPX wrote:enough switch tuning, now it's time to PINCH! (that's what makes the fusion happen)
So presumably they're back to pinching again, probably working their way from 35 kV up to 45 kV, hopefully with none of the previous switch/spark plug/insulator problems.
Temperature, density, confinement time: pick any two.
So presumably they're back to pinching again, probably working their way from 35 kV up to 45 kV, hopefully with none of the previous switch/spark plug/insulator problems.
On August 9, 2011 LPPX wrote:improvements to cathode base to optimize pinching with knife edge underway, piece should be back from machine shop soon
On August 10, 2011 LPPX wrote:checking axial magnetic field coil for any irregularities due to wiggly wires--lookin' good!
On August 10, 2011 LPPX wrote:bolts break -> why? -> measure bolts -> bolts too long -> extract broken bolts -> grind down 16 fresh bolts -> bolts don't break ;-D
On August 10, 2011 LPPX wrote:electrodes - including slotted knife-edge cathode base - back on the machine, that means time to play the slots for fusion!
Temperature, density, confinement time: pick any two.
No more post since that one? I hope it didn't mean that it was the Lab that was actually fusing...
Ivy Matt is just reporting the Twitter updates. The newsletter should be out the next few days. I suppose when Aaron's got a little more time and doesn't need to help out in the lab anymore.
*The FF-1 upgrade is complete.
*FF-1 has been fired numerous times since the upgrade at 35 kV with no misfires and no prefires.
*The new switches have passed a static test at 40 kV with no prefires.
*FF-1 will be tested at 45 kV capacitor bank potential in the latter part of this month.
A test at 45 kV using deuterium fill gas should produce a 2 MA peak current. Testing at 45 kV should also help LPP to determine the optimum gas pressure using deuterium. Once these steps are complete, it's onward to heavier fill gases: deuterium+nitrogen mixes at first, then finally hydrogen+boron.
Temperature, density, confinement time: pick any two.