We've started construction on the site of the world's first fusion power plant, Orion.

Located in Malaga, WA, Orion will begin delivering electricity from fusion to Microsoft by 2028.
This is a big deal! They are moving concrete already! The permits were the hardest part, I heard. Only fusion and some solar are getting permits in WA.
A lot went into securing this site - from initial interconnect studies, working with local community members, and obtaining the world's first Environmental Mitigated Determination of Non-significance for fusion. Can't say enough about our team who Built with urgency over the last year to make this happen!!